प्रदेश नं २, प्रादेशिक कार्यालय जनकपुर

DCS Offices
  • Generic placeholder image
    Janakpur Distribution Center

    041-521614

    041-521614

    Janakpur@nea.org.np

    Loss %(upto Mangsir 2075 B.S) = 36.62

    Length of 33 KV Line = 40 Km

    Length of 11 KV Line = 470 Km

    Length of 400/230 Line = 1650 Km

    No. of Substation = 1 (32 MVA)

    No. Consumer(upto Kartik 2075 B.S) = 83230

    No. of TOD Meter = 81


  • Generic placeholder image
    Rajbiraj Distribution Center

    031-520459

    031-521440

    rajbiraj@nea.org.np

    Loss %(upto Mangsir 2075 B.S) = 41.53

    Length of 33 KV Line = 112.6 Km

    Length of 11 KV Line = 462.45 Km

    Length of 400/230 Line = 1338 Km

    No. of Substation = 2 (16,11 MVA)

    No. Consumer(upto Kartik 2075 B.S) = 72312

    No. of TOD Meter = 24


  • Generic placeholder image
    Jaleshwor Distribution Center

    044-520166

    044520166

    jaleshwor@nea.org.np

    Loss %(upto Mangsir 2075 B.S) = 29.90

    Length of 33 KV Line = 45 Km

    Length of 11 KV Line = 398 Km

    Length of 400/230 Line = 1092 Km

    No. of Substation = 2 (16,8 MVA)

    No. Consumer(upto Kartik 2075 B.S) = 53561

    No. of TOD Meter = 17



  • Generic placeholder image
    Malangwa Distribution Center

    046-520336

    046-521134

    malangawa@nea.org.np

    Loss %(upto Mangsir 2075 B.S) = 26.65

    Length of 33 KV Line = 45 Km

    Length of 11 KV Line = 440 Km

    Length of 400/230 Line = 1050 Km

    No. of Substation = 2 (16,8 MVA)

    No. Consumer(upto Kartik 2075 B.S) = 52687

    No. of TOD Meter = 25



  • Generic placeholder image
    Lahan Distribution Center

    033-560646

    033-561946

    lahan@nea.org.np

    Loss %(upto Mangsir 2075 B.S) = 30.45

    Length of 33 KV Line = 0 Km

    Length of 11 KV Line = 370 Km

    Length of 400/230 Line = 815 Km

    No. of Substation = 1 (32 MVA)

    No. Consumer(upto Kartik 2075 B.S) = 49930

    No. of TOD Meter = 20


  • Generic placeholder image
    Gausala Distribution Center

    044-556165

    044-556165

    gaushala@nea.org.np

    Loss %(upto Mangsir 2075 B.S) = 27.10

    Length of 33 KV Line = 65 Km

    Length of 11 KV Line = 285 Km

    Length of 400/230 Line = 447 Km

    No. of Substation = 2 (16, 3 MVA)

    No. Consumer(upto Kartik 2075 B.S) = 40797

    No. of TOD Meter = 66


  • Generic placeholder image
    Sakhuwa Distribution Center

    041-540461

    041-540461

    sakhuwa@nea.org.np

    Loss %(upto Mangsir 2075 B.S) = 21.74

    Length of 33 KV Line = 11.5 Km

    Length of 11 KV Line = 306.14 Km

    Length of 400/230 Line = 600 Km

    No. of Substation = 2 (8, 24 MVA)

    No. Consumer(upto Kartik 2075 B.S) = 39783

    No. of TOD Meter = 69


  • Generic placeholder image
    Lalbandi Distribution Center

    046-501729

    046-501729

    lalbandi@nea.org.np

    Loss %(upto Mangsir 2075 B.S) = 24.33

    Length of 33 KV Line = 64 Km

    Length of 11 KV Line = 158 Km

    Length of 400/230 Line = 1100 Km

    No. of Substation = 1 ( 24 MVA)

    No. Consumer(upto Kartik 2075 B.S) = 36267

    No. of TOD Meter = 46


  • Generic placeholder image
    Siraha Distribution Center

    033-520115

    033-520115

    siraha@nea.org.np

    Loss %(upto Mangsir 2075 B.S) = 24.60

    Length of 33 KV Line = 31 Km

    Length of 11 KV Line = 214.31 Km

    Length of 400/230 Line = 424.24 Km

    No. of Substation = 1 ( 16 MVA)

    No. Consumer(upto Kartik 2075 B.S) = 35448

    No. of TOD Meter = 4


  • Generic placeholder image
    Udayapur Distribution Center

    035-420629

    035-420629

    udayapur@nea.org.np

    Loss %(upto Mangsir 2075 B.S) = 2.02

    Length of 33 KV Line = 51.71 Km

    Length of 11 KV Line = 350.28 Km

    Length of 400/230 Line = 725.62 Km

    No. of Substation = 2 ( 25, 3 MVA)

    No. Consumer(upto Kartik 2075 B.S) = 34645

    No. of TOD Meter = 19



  • Generic placeholder image
    Sindhuli Distribution Center

    047-521105

    047-521105

    sindhuli@nea.org.np

    Loss %(upto Mangsir 2075 B.S) = 10.09

    Length of 33 KV Line = 45 Km

    Length of 11 KV Line = 267.5 Km

    Length of 400/230 Line = 703.73 Km

    No. of Substation = 2 ( 8, 1.5 MVA)

    No. Consumer(upto Kartik 2075 B.S) = 28781

    No. of TOD Meter = 21


  • Generic placeholder image
    Mirchaiya Distribution Center

    033-550509

    033-550509

    mirchaiya@nea.org.np

    Loss %(upto Mangsir 2075 B.S) = 6.17

    Length of 33 KV Line = 34 Km

    Length of 11 KV Line = 220 Km

    Length of 400/230 Line = 500 Km

    No. of Substation = 1 ( 8 MVA)

    No. Consumer(upto Kartik 2075 B.S) = 28723

    No. of TOD Meter = 18


  • Generic placeholder image
    Diktel Distribution Center

    036-420636

    036-420636

    diktel@nea.org.np

    Loss %(upto Mangsir 2075 B.S) = 14.80

    Length of 33 KV Line = 69 Km

    Length of 11 KV Line = 386.77 Km

    Length of 400/230 Line = 755.41 Km

    No. of Substation = 1 ( 1.5 MVA)

    No. Consumer(upto Kartik 2075 B.S) = 12324

    No. of TOD Meter = 16


  • Generic placeholder image
    Okhaldhunga Distribution Center

    037-540205

    037-540205

    okhaldhunga@nea.org.np

    Loss %(upto Mangsir 2075 B.S) = 4.65

    Length of 33 KV Line = 33 Km

    Length of 11 KV Line = 163 Km

    Length of 400/230 Line = 260 Km

    No. of Substation = 1 ( 2.25 MVA)

    No. Consumer(upto Kartik 2075 B.S) = 5613

    No. of TOD Meter = 1



Check Mail